|
Northeast Zone
Includes
Aitkin, Carlton, Cass, Cook, Crow Wing, Isanti, Itasca, Hubbard,
Kanabec, Koochiching, Lake, Mille Lacs, Morrison, Pine, St.
Louis, Todd and Wadena counties.
Detailed
Northeast Planning Zone Map (PDF)
2007
Public Information Meeting
The
public was invited to join representatives from area utilities
in a planning meeting to discuss the electric transmission
system in Minnesota and the Upper Midwest.
Discussion
focused on identifying problems with the existing system in
meeting the demand for electricity in the area and possible
solutions, including possible new transmission projects. A
synopsis of public comments from the meeting will be included
in a Biennial State Transmission Plan the utilities will submit
to the Minnesota Public Utilities Commission (MPUC). The plan
will also include a list of transmission lines each utility
is requesting certification from the MPUC to build. The MPUC
will provide opportunity for public comment on the plan.
Public
participation is an important part of the transmission planning
process as we work together to ensure continued reliable service
to Minnesota residents.
Issues
Specific to This Zone
Cromwell-Wrenshall-Mahtowa
Area
• Improvements needed for local load serving
• Low voltage for loss of Thompson source
• Studies underway to determine best method to address
this inadequacy
• Options include 115-kV transmission and local area
generation
• The transmission option may also provide a benefit
to the issues Great River Energy is having in the Floodwood
area
Central Lakes Area
• Facility overloading occurs on the Minnesota Power
115-kV system that serves the Brainerd substation
• Need a 115-kV line connection between Southdale and
the Minnesota Power 24 Line (Baxter-Dog Lake)
• This connection will improve transmission reliability
to Southdale and Brainerd substations by adding a third source
to the region
Pierz-Genola Area
• Contingency conditions will result in low voltage
and facility overloading
• The future plans call for a new 115-kV line to Little
Falls from the Pierz area where a 230/1150-kV source will
be located
• Present plans would be to build the line and operate
at 34.5-kV
• Great River Energy is also considering to shorting
the line in the short-term by moving the Crow Wing Power Little
Falls substation to 115-kV
Taconite Harbor to Grand Marais
• The existing 69-kV system in a long radial line where
loss of the lines leads to potentially long outages
• Great River Energy will install a small generation
plant to provide backup service to this area
Mille Lacs Area
• The existing transmission system in this area has
already become limited in service where low voltages are already
forecasted during contingencies on peak loads
• Facility overloads are expected in the next 10 years
• The proposed alternative is a new Mud Lake-Wilson
Lake 115-kV line and Wilson Lake 115/69-kV source in 2008
• Great River Energy filed a certificate of need and
route permit in July, 2006 to the MN PUC
Floodwood Area
• It is projected that by 2012, contingency conditions
will result in low voltage
• Facility overloads at a later time
• Proposed alternative is a new 115/69-kV substation
in the Floodwood area
• Great River Energy and Minnesota Power coordinating
study with Wrenshall and
Mahtowa area study
Nashwauk Area
• Low voltages and facility overloading can occur during
system intact conditions
• Two alternatives are being reviewed
• Alternative 1 is a new substation at Shoal Lake
• Alternative 2 is a new substation at Lawrence Lake
• Lawrence Lake is the preferred option as the substation
is located closer to the load center
Bemidji-Grand
Rapids 230-kilovolt transmission line
• The Bemidji and Cass lake area electric load will
soon reach levels that will make its electric system susceptible
to brown-outs or black-outs without the construction of another
230-kV line
• This proposed project will provide increased voltage
support not only to the Bemidji and Cass Lake area, but also
throughout the Red River Valley and north central Minnesota.
• CapX 2020 planning efforts also identified the Bemidji-Grand
Rapids line as one of four lines needed in the first group
of projects to improve regional transmission system reliability
Other Projects
• Mesaba Energy Project Outlet Transmission
• Generator outlet (GO) transmission is necessary to
deliver the plant output to the Minnesota Power transmission
network at either the Forbes or Blackberry 230-kV Substations
• The proposed GO transmission lines involve the construction
of two 345-kV circuits but operated at 230-kilovolt for the
first unit
• The application for the plant site selection and the
GO transmission routings was accepted by the MN PUC as complete
on July 28, 2006
• The Large Generator Interconnection Agreements covering
the required Network Upgrades and Interconnection Facilities
for both the proposed sites have been completed and executed
by MISO, Minnesota Power and Excelsior Energy.
• For the preferred West Range site, a new 80 mile 230kV
line from Boswell-Riverton is required in addition to the
normal Point of Interconnection substation modifications.
• Expect the draft EIS to be issued around Labor Day
and the public hearings to follow.
• Expect site/GO line public hearings to start in September
2007 and a final MN PUC ruling by March-April, 2007.
Transmission
to serve Minnesota Steel Industries
• Transmission will be needed to supply possible new
mining/steel making facility proposed to be located near Nashwauk
Minnesota
• Transmission construction would involve development
of 230 kV lines to connect facility to area’s transmission
system
• Route Permit expected to be filed 2007
• Transmission construction would proceed only if Minnesota
Steel Industries project proceeds
Project Updates
Tower-Ely-Babbitt Area Tracking # 2003-NE-N1
• Certificate of need and route permit have been obtained
• Right-of-way acquisition and construction to start
fall 2007
• Project expected to be complete November 2009
Pequot
Lakes-Badoura Area and Long Lake-Badoura Area Tracking # 2003-NE-N3
and 2005-NE-N1
•
Certificate of need issued June 2006
• Route permit application submitted March 2007
• Right-of-way acquisition and construction expected
to start late fall 2007 if permit obtained
• Project expected to be complete Spring 2010
Swanville
area
• Permit for Pepin Lake Substation approved
• Substation Construction to start Fall 2007
• Project expected to be complete Fall 2008
Two
Harbors area
• Permit for 115 kV Substation approved
• Substation Construction to start Fall 2007
• Project expected to be complete November 2008
Contact
us:
Additional
comments or questions may be submitted by using the “Contact
Us” link at the top of this web page.
|